Build, Buy, Keep, Replace, or Stop Decisions
A council had spent two years discussing replacement of its benefits-administration system. Vendor offers covered five years; the internal build estimate covered three and omitted the builders’ salaries. Keeping the system had no comparable estimate, even though it depended on two contractors and a database approaching the end of support. The finance director asked for complete alternatives over one period, including the work required to keep the current service acceptable. That request exposed a second problem: the committee was treating build, buy, keep, replace, and stop as five separate options, although its proposed purchase was also a replacement.
The council is fictional. Its decision illustrates how to combine those five verbs into strategies that can be assessed. Build and buy concern how a capability is obtained; keep, replace, and stop concern what happens to an existing capability. One strategy can combine them. The work is to define comparable service outcomes, exclude infeasible choices, estimate future costs and benefits, test uncertain assumptions, and assign responsibility for reconsidering the decision.
The candidate tests are developed in technology selection. The assessment of an existing estate and its migration strategies appears in Mapping Systems to Hosts. Contract and relationship management after selection is covered in The Supplier Changed Its Roadmap and Ours Changed With It. Here those inputs support a choice among complete strategies.
Combine the verbs before comparing the options
The build or buy decision may combine internal development, a configured product, supported extensions, and specialists hired to build a component. GOV.UKโs purchasing guidance discusses such combinations. Its reasons to consider building include unusual needs, limited supplier fit, integration constraints, desired control, and the capability to manage development. Reasons to consider buying include market fit, suitable configuration, limited need for bespoke changes, available specialist support, and the ability to support the purchase. These considerations inform investigation; they are not a universal set of mandatory gates.
Configuring a product uses its supported settings and features. Customization can create additional upgrade, support, and removal work, so test the particular extension mechanism and contract. Buy-to-build means procuring a team to develop technology. It does not by itself transfer ownership of all resulting code. Agree rights for new work, existing assets, and third-party components, including continued use, modification, and transfer. The UK Intellectual Property Office distinguishes commissioned work from work created in employment; applicable law and written agreements matter.
| Decision | What must be established |
|---|---|
| Build or buy | A feasible combination of implementation, support, rights, and operating responsibility. Compare concrete candidates and revise the sourcing approach as evidence improves. |
| Keep | The retained service can meet mandatory conditions, including funded remedies where needed. Compare its future costs, benefits, and accepted residual risk. |
| Replace | A successor and transition can meet required conditions, with benefits and risks that justify the change. The current service need not be failing for replacement to be worthwhile. |
| Stop | The organization may end this activity, with remaining needs, dependents, records, and service obligations addressed. Stopping a local implementation may still require a replacement service. |
The council could not choose an unsupported service merely because it was cheaper. Its keep option therefore included a supported database upgrade and operator coverage. Any permitted risk acceptance needed an authorized owner and limits; an internal decision could not waive an external obligation. The same acceptance discipline applied to the proposed successors. A low estimate could rank an acceptable option more favorably, but could not make a failed requirement disappear.
GOV.UKโs legacy guidance treats support, cost, change limitations, and risk as reasons to reconsider the current system. AWS lists prolonged absence of inbound traffic as a retirement candidate signal. Neither a quiet ninety days nor a low utilization figure proves that a service is unnecessary: annual batches, outbound feeds, and manual work may be missing from the observation. Investigate dependencies in both directions, check infrequent work and retained-record access, and use a controlled stop and tested recovery where appropriate. The sequence is explained in system retirement.
Make the cost boundary explicit
Estimate total cost of ownership over a common period, workload, and service scope. Include acquisition, transition, operation, change, and the exit or residual obligations at the comparison boundary. A supplier may price transition assistance in its offer; other migration, validation, and retirement work may remain the customerโs responsibility. Verify the coverage rather than assuming every quote includes it or none does. Open-source software also requires operating, migration, and support resources, as GOV.UKโs open-source guidance emphasizes.
Exclude sunk costs that the current choice cannot change. Compare future costs and benefits, including the opportunity cost of resources already owned. A paid-for server may have an alternative use or resale value; already employed staff may have valuable work displaced by this assignment. Resource opportunity cost and additional cash payments are different views. State which view the comparison uses and reconcile them rather than adding two valuations of the same resource.
Use one baseline for benefits as well. Suppose keeping costs 100, replacement costs 110, and replacement adds a benefit worth 20. Its incremental net benefit is 20 โ (110 โ 100) = 10. Adding the missed benefit to keepโs cost and also counting it as replacementโs benefit would produce 30, counting the same improvement twice. Distinguish actual change expenditure, unmet outcomes, and expected incident losses. Check for overlap between risk estimates, mitigation costs, and uncertainty allowances. The broader budget treatment is developed in The Case Said Four Million and the Cost Was Nine.
Separate entering a successor from leaving it later
Dependence can be worth accepting when a service removes valuable work. Technical lock-in identifies the technical dependencies that make switching difficult; the exit cost includes rebuilding logic, operations, skills, and integrations as well as moving data. GOV.UK recommends estimating the time and cost of leaving after temporary benefits lapse and reassessing the estimate during use. An internal build may be handed to another operator with its code intact, partly adapted, or replaced. Its exit is not necessarily a rewrite.
The council assessed two separate transfers. First, it tested export from the current system. In a deliberately selected sample of 1,000 records covering difficult relationship and history cases, 120 required manual repair. The 12% described that diagnostic sample, not an unbiased population estimate. The team investigated the affected structures, reconciled repairs against retained source records and paper evidence, and budgeted an illustrative 0.2 million repair package in each replacement option. A better successor could not recreate information absent from its input. The package remained an estimate to refine before commitment.
Second, the team tested each candidateโs own future export and a representative import elsewhere. Those tests informed separate end-of-period exit estimates. They checked identifiers, relationships, history, permissions, required behavior, and the rights to transfer them. Coverage gaps, scale, and untested workflows remained visible. The portability and exit plan records those limits, the transfer sequence, usable access before deletion deadlines, owners, and recovery arrangements. A successful sample is evidence within its scope, not proof that the complete service is reversible.
Agree the disposition of copies after return and validation. Delete those that must be deleted and document any legally required retention, its scope, duration, access restrictions, and eventual disposal. ICO guidance for controllerโprocessor contracts includes an exception where the law requires storage. GOV.UKโs retirement guidance also requires continued protection of retained information. Apply the relevant jurisdiction and roles; contract termination alone authorizes neither indefinite retention nor indiscriminate deletion.
A comparison the committee can calculate
The following figures are invented to demonstrate the councilโs calculation. Amounts are millions of pounds over ten years from the decision, for the same core service and demand. This is a simplified payment comparison: zero inflation, no discounting, transition spending grouped at year 0, operating payments at each year end, and the stated exit package at the end of year 10. Assume no residual asset proceeds. Real transition schedules, renewal terms, and remaining assets or liabilities require their own estimates. This arithmetic is not a Green Book social-value appraisal.
Each strategy includes the same separately approved withdrawal of an obsolete local module whose work has moved to a national service. The council has confirmed the remaining usersโ route, dependencies, retained-record access, and recovery arrangements before approving that withdrawal. Its costs are included in each initial package. The rest of the service must continue: stopping the entire service fails its obligations and is excluded with that reason recorded. The four feasible proposals below have the same required accuracy, access, and service outcomes. Product B additionally offers a validated route for avoiding some separately billed manual checks. The other proposals do not include that enhancement in their current scope.
| Payment item | K: improve and keep | D: build a replacement | A: replace with product A | B: replace with product B |
|---|---|---|---|---|
| Initial package: implementation, transition, and old-path retirement | 0.8 | 3.0 | 1.0 | 2.0 |
| Annual operating payment ร 10 | 0.9 ร 10 = 9.0 | 0.5 ร 10 = 5.0 | 0.45 ร 10 = 4.5 | 0.45 ร 10 = 4.5 |
| End-of-period exit and retained-record package | 0.2 | 0.4 | 0.5 | 0.4 |
| Manual checking baseline before Bโs reduction | 2.0 | 2.0 | 2.0 | 2.0 |
| Total before the checking reduction | 12.0 | 10.4 | 8.0 | 8.9 |
Initial packages include implementation labor, integration, training, dual running, and the current systemโs retirement where replaced. Each replacement package contains the 0.2 repair estimate above. Operating lines include paid staffing, support, hosting, licenses, and planned changes; the separate checking line is excluded from those lines. Exit packages cover the serviceโs assumed disposition at the ten-year boundary and the costed arrangements for records retained afterward. If that disposition changes, revise the boundary costs rather than charging a fictional termination. Existing unavoidable payments common to all choices are treated consistently; no past purchase price is charged again.
Product A has the lowest total before the checking reduction. Product Bโs higher initial package includes integration of the new checking workflow and a council-maintained adapter for eligibility rules. The adapterโs operation and eventual replacement are included in its estimates. Separating rules can reduce work during a later move, but its maintenance and the replacementโs capabilities determine the net effect. Likewise, delaying retirement can add operating risk while reducing a particular termination charge. Neither the option name nor a longer horizon fixes the direction of the cost difference.
Calculate what would change the choice
Bโs additional value is a hypothesis to test against a baseline, following the discipline in Live for a Year, Used by a Third. Assume 100,000 eligible claims over the ten years. Each qualifying claim completed through Bโs validated workflow avoids a ยฃ20 external checking payment under the stated contract. The quality checks must show that this route preserves the required outcomes. Failed or manual cases retain the charge. The assumption is about payments actually avoided, not payroll savings inferred from time released.
Let a be the fraction of those 100,000 claims that qualify for the avoided charge, from 0 to 1. Full use would avoid 2.0 million, so the modeled reduction is 2a. Bโs total becomes 8.9 โ 2a, while A remains 8.0. Setting them equal gives 8.9 โ 2a = 8.0, hence a = 0.45. At 60%, B costs 7.7 and is 0.3 cheaper than A. At 30%, it still avoids 0.6 of payments but costs 8.3 and loses to A. The 45% threshold is a change in the ranking, not the first appearance of a benefit and not break-even against keeping, which costs 12.0 in this model. Count the saving either as this cost reduction or as an incremental benefit, never both.
The denominator is eligible claims over the full horizon, not distinct users or the take-up rate at the end of year two. Estimate cohort volumes and the adoption ramp, including failed and unobserved cases, to support a forecast of a. A 60% forecast remains uncertain. It does not authorize wider use before workflow, permission, capacity, and recovery conditions are met. If payment terms impose a minimum quantity or checking is no longer removable, the linear saving model must change.
GOV.UKโs appraisal guidance calls for evidence-based optimism bias adjustments in its public-appraisal context. For an actual decision, calibrate estimates with comparable outturns and avoid overlapping allowances. The table above is deliberately a base-case illustration, not a risk-adjusted approval budget. Its switching value is conditional on the other inputs. If Bโs initial package rises by 0.4, its boundary becomes (8.9 + 0.4 โ 8.0) / 2 = 65%; a 60% forecast would then be insufficient. Test plausible combinations of changes, not just one variable at a time.
| Uncertainty | What to examine |
|---|---|
| Service horizon and payment timing | Recalculate annual flows, renewal and support terms, exit obligations, and residual values. For economic appraisal, apply the appropriate price basis and discounting. |
| Bespoke change demand | Estimate the actual kinds of change and their development, support, and upgrade costs under each proposal. Reconsider a hybrid design where useful. |
| Data repair and future portability | Keep current-source repair separate from each successorโs later exit. Expand tests around consequential coverage gaps and update the cost range. |
| People and adoption | Model operator loss, replacement capacity, eligible claim volumes, workflow success, and the payment terms that turn use into savings. |
Give the decision an owner and a review trigger
The logic of pilot exit criteria applies beyond a trial: state what evidence supports the next commitment, who obtains it, and what the review may decide. Record both scheduled reviews and material triggers. A trigger reopens the comparison; it does not automatically choose a replacement. Recompute the remaining costs and benefits from that decision date, excluding what has become sunk. Preserve the original forecast so that changes remain explainable.
| Current commitment | Review trigger | Decision responsibility and possible response |
|---|---|---|
| Internal development | Critical knowledge becomes concentrated or estimated change demand shifts | The service and engineering owners compare remaining development, maintenance, purchase, and transition options; fund a remedy, pause, or change scope where permitted. |
| Purchased service | Capability withdrawal, renewal change, or failed exit rehearsal | The service and contract owners assess existing rights, renegotiation, renewal, and a feasible exit. |
| Retained system | Support deadline approaches, cost or risk changes, or a required outcome is at risk | The lifecycle owner starts early enough for assessment, approval, transition, and contingency; a cheap estimate does not waive a mandatory condition. |
| Replacement program | Validation fails, costs change, or adoption undermines expected value | The program and benefit owners apply the approved stop criteria. Use fallback only within its tested state, compatibility, and time limits; otherwise use the approved recovery path or revise the plan. |
| Retired activity | A required consumer or unmet need is discovered | The named owner for remaining obligations investigates, restores authorized access where appropriate, and reopens the service decision without assuming the retired application can restart unchanged. |
Migration decisions need the reconciliation, authority transfer, and recovery evidence described in The Counts Matched and the Totals Did Not. A late benefits review may occur after the fallback window has closed. Continuing with a written explanation cannot substitute for a required safety or service condition. The reviewer must identify who can approve a changed scope and which obligations remain binding.
What the decision record should let a reviewer check
A reviewer should be able to reconstruct the alternatives, their service boundaries, and why excluded options were infeasible. The cost schedule should identify what the organization pays, which resource costs are considered separately, and where each benefit enters once. Data-transfer evidence should distinguish the current exit from the successorโs future exit. Each consequential estimate needs an owner, uncertainty, and an observation that could change it. Record the decision, accepted risks, next commitment, review triggers, and responsibility for the service that remains.
In this version of the councilโs case, B is preferred under the base assumptions because its 7.7 modeled payment total is lower than Aโs 8.0, while the mandatory outcomes remain satisfied. The committee authorizes a bounded next stage to validate the repair package, contract savings, implementation cost, and achievable claim coverage before the full commitment. The 65% stress scenario remains visible. The old system retains an operating owner during that work, and the local module closes only after its separate retirement conditions are met. The decision combines buying a successor, building an adapter, replacing the core system, temporarily keeping the old path, and stopping one activity. The record explains that combination and the evidence still needed to proceed.
References:
- GOV.UK, Define your purchasing strategy (Technology Code of Practice point 11; OGL v3.0).
- UK Intellectual Property Office, Ownership of copyright works โ commissioned works and employment.
- GOV.UK, Be open and use open source (TCoP point 3; OGL v3.0).
- GOV.UK, Managing legacy technology (2019; OGL v3.0).
- GOV.UK, Managing technical lock-in in the cloud (OGL v3.0).
- GOV.UK Service Manual, Retiring your service (OGL v3.0).
- HM Treasury, The Green Book (2026) โ costs, benefits, risk, discounting, and switching values (OGL v3.0).
- AWS Prescriptive Guidance, About the migration strategies.
- AWS Prescriptive Guidance, Best practices for assessing applications to be retired.
- ICO, Contracts โ end-of-contract provisions.